Chevron delays Gorgon Train 2 restart

US oil and gas major Chevron on Wednesday said that it would need additional time to complete repairs of propane heat exchangers on the second train at its Gorgon liquefied natural gas (LNG) project at Barrow Island.

Weld quality issues were discovered during scheduled maintenance in July this year, and the oil and gas producer had initially hoped to restart the train early this month. However, restart production has now been pushed back to October.