The target date for commissioning at emerging African plant nutrient feed minerals producer Kropz’s Elandsfontein phosphate project has been moved to the fourth quarter of 2021. The move is as a result of additional test work being required, as well as the design and delivery of long-lead capital items and associated works, which have impacted on both timing and the capital cost to first production.