Nevada Gold Mines plans power switch to lower carbon emissions

Nevada Gold Mines (NGM) – a joint venture (JV) between Barrick Gold and Newmont – will convert its TS coal power plant to a dual fuel processing, allowing the facility to generate power from natural gas. The JV is also mulling the potential for a 200 MW solar facility with battery storage.

NGM aims to start the conversion process at TS later this year, with the company currently working with the state of Nevada on final permitting to allow for construction to begin towards the end of 2020 and final commissioning planned for the second quarter of 2022.

The conversion of NGM will enable the facility to reduce carbon emissions by as much as 50%, 61.5% shareholder and operator, Barrick said in a statement on Monday.