Construction activities at the Barruecopardo tungsten project, in Spain, have begun to wind down and mine commissioning activities are ramping up significantly, in line with a previously guided timeline of starting production in early February.
London-listed Ormonde Mining reported on Friday that the construction of the turnkey crush and screen plant was completed in September, with ‘cold’ commissioning completed during October and ‘hot’ commissioning currently ongoing.