Company News – Tue 9 Oct, 2018

By Cory댊 More high Grade Drill Results From Osisko Metals – 21.47% Zinc+Lead Over 9.98 Metres

Here are the assays from a further 14 holes out of Osisko Metals at the Pine Point project. It’s important to remember that this drilling to being use to confirm old work with a goal to release an inferred resource in the near term. In these drill results we continue to see some very impressive high-grade near surface hits.

Please email me with any questions you have for the team at Osisko Metals – Fleck@kereport.com.

Click here to visit the Osisko Metals website for further information.

…Here’s the news…

MONTREAL, Oct. 09, 2018 (GLOBE NEWSWIRE) — Osisko Metals Incorporated (the “Company” or “Osisko Metals”) (TSX-V: OM; FRANKFURT: OB51) is pleased to announce assay results from 14 drill holes completed in the East Mill Zone in the Pine Point Mining Camp (“PPMC”). Drill hole EM-18-PP-140 intersected 13.91% Zinc and 7.56% Lead (21.47% Zinc + Lead) over 9.98 metres and hole EM-18-PP-152 intersected 4.22% Zinc and 2.56% Lead (21.47% Lead + Zinc) over 8.20 metres.

All intersections are within a flat lying tabular-style deposit known as K-32 and all intercepts are located above 42 metre depths. (See 2018 Summer Drill East Mill Zone K-32).

The historical K-32 deposit currently measures 410 metres in strike length with an average mineralized width of approximately 65 metres. It occurs within the East Mill Zone that hosts eight historical deposits containing unclassified historical resources reported by Cominco Ltd. (1988). The K-32 deposit is located along the main haulage road, 3.9 kilometres to the east of the existing electrical sub-station and former mill site. The East Mill Zone extends 7.6 kilometres to the east of the electrical substation and is adjacent to the main haul road along its entire length. Additional highlights are listed below in Table 1 and details are provided in Tables 2 & 3.

Table 1: Selected Drill Highlights

Hole Name Area Historical
Deposit
From To Width Zinc Lead Zinc + Lead
(metres) (metres) (metres) % % %
EM-18-PP-140 East Mill K-32 14.32 24.30 9.98 13.91 7.56 21.47
EM-18-PP-152 East Mill K-32 16.95 25.15 8.20 4.22 2.56 6.78

The objective of the 2018 drill program is to upgrade approximately 50 million tonnes of unclassified near-surface historical resources within known deposits (Cominco Ltd.) to NI43-101 Inferred Mineral Resources as quickly as possible in areas amenable to open pit mining. This will then be used as a resource base for future economic studies.

The 2018 drill program consists of approximately 700 drill holes within the Main Trend, a 20-kilometre long, portion of the PPMC that is located on the south shore of Great Slave Lake in the Northwest Territories, near infrastructure and paved highway access and with 100km of haulage roads already in place.

Note regarding historical resource and Qualified Person

The above-mentioned historical resources do not conform to National Instrument 43-101 standards. The Company is reporting the historical estimates for reference purposes only. Neither Osisko Metals nor its consultants have completed sufficient work to verify the historical estimates and these should not be relied upon for investment purposes. A Qualified Person has not done sufficient work to classify the historical estimates as NI43-101 compliant mineral resources and there is no guarantee that such work will allow conversion of such historical resources.

Stanley G. Clemmer, P. Geo registered in the Northwest Territories and is Chief Geologist for Pine Point Mining Limited, a wholly owned subsidiary of Osisko Metals Limited. He is the Qualified Person responsible for the technical data reported in this news release.

Quality Assurance / Quality Control

Osisko Metals adheres to a strict Quality Assurance and Quality Control program with regard to core handling, sampling, transportation of samples and lab analyses. Drill core samples from the Pine Point project area were securely transported to its core facility in Hay River, Northwest Territories where they were logged and sampled. Samples selected for assay were shipped via secure transportation to the ALS Canada Ltd.’s preparation facility in Yellowknife. Pulps were analyzed at the ALS Canada Ltd. facility in North Vancouver, British Columbia. All samples are analyzed by four acid digestion followed by both ICP-AES and ICP-MS for ultra-trace level detection for a multi-element suite with a 1% upper detection limit for base metals. Samples reporting over 1% for Zn and 1% for Pb are analyzed by assay grade four acid digestion and ICP-AES analysis with an upper detection limit of 30% and 20% respectively. Samples reporting Zn >30% and or Pb >20% are analyzed by traditional titration.

Table 2: Composite Assay Results

Hole Name Historical
Deposit
From To Drilled Width True Width Zinc Lead Zinc + Lead
(metres) (metres) (metres) (metres) % % %
EM-18-PP-114 K-32 17.20 18.55 1.35 1.35 7.79 0.51 8.31
EM-18-PP-118 K-32 No Significant Results
EM-18-PP-126 K-32 16.41 19.47 3.06 3.06 6.03 1.25 7.29
EM-18-PP-140 K-32 14.32 24.30 9.98 9.98 13.91 7.56 21.47
EM-18-PP-141 K-32 19.50 19.90 0.40 0.40 5.89 0.02 5.91
EM-18-PP-141 K-32 22.70 24.90 2.20 2.20 5.18 0.16 5.34
EM-18-PP-141 K-32 34.05 34.80 0.75 0.75 1.72 0.18 1.90
EM-18-PP-152 K-32 13.15 14.05 0.90 0.90 2.80 0.28 3.08
EM-18-PP-152 K-32 16.95 25.15 8.20 8.20 4.22 2.56 6.78
EM-18-PP-152 K-32 26.45 27.25 0.80 0.80 1.02 0.01 1.02
EM-18-PP-153 K-32 8.53 10.21 1.68 1.68 2.69 0.66 3.35
EM-18-PP-153 K-32 18.93 19.33 0.40 0.40 3.24 1.17 4.41
EM-18-PP-154 K-32 No Significant Results
EM-18-PP-155 K-32 10.27 11.20 0.93 0.93 1.73 0.17 1.91
EM-18-PP-156 K-32 9.00 11.75 2.75 2.75 2.04 1.49 3.53
EM-18-PP-158 K-32 10.67 12.60 1.93 1.93 1.21 2.09 3.30
EM-18-PP-158 K-32 15.52 16.24 0.72 0.72 2.86 0.55 3.41
EM-18-PP-159 K-32 8.41 9.30 0.89 0.89 1.66 0.74 2.40
EM-18-PP-159 K-32 12.99 13.44 0.45 0.45 0.76 3.43 4.19
EM-18-PP-160 K-32 9.00 9.78 0.78 0.78 4.10 0.98 5.08
EM-18-PP-181 K-32 12.13 14.94 2.81 2.81 5.74 0.60 6.34
EM-18-PP-181 K-32 19.00 20.00 1.00 1.00 1.35 0.01 1.35

Table 3: Drill hole collar locations (UTM NAD83 zone 11)

Hole Name Area Deposit Easting Northing Elevation Azimuth Dip Depth (metres)
EM-18-PP-114 East Mill K-32 643585.9 6752407.6 214.18 0 -90 45.00
EM-18-PP-118 East Mill K-32 643815.6 6752474.3 215.40 0 -90 42.00
EM-18-PP-126 East Mill K-32 643695.5 6752398.6 215.99 0 -90 42.00
EM-18-PP-140 East Mill K-32 643542.9 6752316.9 214.76 0 -90 42.00
EM-18-PP-141 East Mill K-32 643491.8 6752319.8 214.98 0 -90 43.10
EM-18-PP-152 East Mill K-32 643493.4 6752266.3 214.97 0 -90 42.00
EM-18-PP-153 East Mill K-32 643490.3 6752158.6 214.79 0 -90 42.00
EM-18-PP-154 East Mill K-32 643524.5 6752169.8 215.06 0 -90 42.00
EM-18-PP-155 East Mill K-32 643537.9 6752130.4 215.00 0 -90 42.00
EM-18-PP-156 East Mill K-32 643554.4 6752181.1 214.77 0 -90 42.00
EM-18-PP-158 East Mill K-32 643538.3 6752260.2 214.77 0 -90 42.00
EM-18-PP-159 East Mill K-32 643581.7 6752254.7 214.71 0 -90 42.00
EM-18-PP-160 East Mill K-32 643550.6 6752284.6 214.72 0 -90 42.00
EM-18-PP-181 East Mill K-32 643531.6 6752079.7 214.61 0 -90 42.00

About Osisko Metals

Osisko Metals is a Canadian exploration and development company creating value in the base metal space with a focus on zinc mineral assets. The Company controls Canada’s two premier historical zinc mining camps, namely the Pine Point Camp (“PPMC”) located in the Northwest Territories (22,000 ha) and the Bathurst Mining Camp (“BMC”), located in northern New Brunswick (63,000 ha). The Company is currently drilling in both camps for a combined total 100,000 metre program. The focus of these programs is to upgrade historical resources to NI43-101 standards and also to pursue exploration around historical deposits. Brownfield exploration includes new innovative 3D compilation techniques, updated geological interpretation, and modern geophysics. In Québec, the Company owns 42,000 hectares that cover 12 grass-root zinc targets that will be selectively advanced through exploration. In parallel, Osisko Metals is monitoring several base metal-oriented peers for opportunities.

For further information on Osisko Metals, visit www.osiskometals.com or contact:
Jeff Hussey
President & CEO
Osisko Metals Incorporated
(514) 861-4441
Email: info@osiskometals.com
www.osiskometals.com
Christina Lalli
Director, Investor Relations
Osisko Metals Incorporated
(438) 399-8665
Email: clalli@osiskometals.com
www.osiskometals.com

Cautionary Note Regarding Forward-Looking Information

This news release contains “forward-looking information” within the meaning of applicable Canadian securities legislation based on expectations, estimates and projections as at the date of this news release. Forward-looking information involves risks, uncertainties and other factors that …read more

From:: The Korelin Economic Report