TSX-listed exploration and development company African Gold Group reports its definitive feasibility study (DFS) on an expanded throughput scenario on process plant at the Kobada gold project in southern Mali, has been completed, suggesting the process plant could be ramped up to exceed the DFS target of 100 000 oz/y.
Mineral processing project management and engineering firm SENET conducted the definitive feasibility study for the plant, which is a three-million ton a month run-of-mine feed combined with a gravity circuit and a carbon-in-leach (CIL) section.