China equipment delay hits Caucharí-Olaroz construction timeline

The construction schedule of the Cauchari-Olaroz lithium project, in Argentina, will be reassessed to account for delays in the delivery of equipment for the chemical plant, Vancouver-based Lithium Americas reported on Friday.

The company said that several pieces of equipment were being fabricated in China and that some suppliers had sub-vendors fabricating in China.

As a result of the recent outbreak of the new coronavirus, Covid-19, which closed factories and business in China for an extended period, there could be delays of up to 90 days in the delivery time for some of the items.