Lundin Gold (TSX: LUG) reported Thursday afternoon that ramp-up to commercial production is on schedule and on budget at its Fruta del Norte gold project in southeast Ecuador. A total of 28,678 ounces of gold were produced by the end of 2019.
Of the total production at Fruta del Norte, 3,411 ounces of gold were produced in the form of doré and 25,267 ounces were produced as concentrate. Approximately 3,400 tonnes of concentrate were produced, of which 2,676 tonnes were shipped to a smelter in Finland by year-end.
“We produced first gold on schedule and on budget and exported our first shipments of concentrate and doré in the fourth quarter of last year,” said Ron Hochstein, president and CEO of Lundin Gold.
Ramp up is currently progressing well, and the company expects to reach commercial production on schedule in the second quarter of 2020.
Construction progress was 99.2% complete as at year-end. Only the paste plant and the Zamora River bridge remain to be completed, which are anticipated to occur in the second and third quarters of 2020, respectively.