Lucara going ahead with $514m expansion of Karowe mine

Canada’s Lucara Diamond (TSX:LUC) has given the green light to a planned underground expansion of its Karowe mine in Botswana, which is expected to extend the operation’s life for 20 years until 2040.

The Vancouver-based miner said the project, which
pre-production costs have been pegged at $514 million, will be largely financed
from cash resources with external funding described by Lucara’s chief financial
officer, Zara Boldt, as “modest”. 

While the company investment is expected to be paid back in under three years, it has moved to preserving cash by suspending dividends for future quarters.

While the needed investment is expected to be paid back in under three years, Lucara has suspended dividends.

Moving Karowe underground, however, will allow Lucara to
exploit the highest value part of the orebody first and generate over $5.25
billion in gross revenue, president and chief executive officer, Eira Thomas,
noted.

She also said that margins remained healthy as Lucara’s
conservative diamond pricing models reflected the current “difficult” market
environment. 

“Lucara’s short-term view is that the market is now
stabilizing,” said Thomas. “Longer term, the fundamentals are
expected to strengthen in line with supply shortfalls from mature, depleting
mines in Australia and Canada. It is important to note that a return to diamond
prices observed in 2015 would nearly double the net present value (5%) of this
project to $1.4 billion.”

Construction is expected to start by mid-2020 with the first
diamond-bearing underground ore due for milling in 2023. 

Karowe is one of the world’s most prolific sources of large, high value
type IIA diamonds. Since beginning commercial operations in 2012, it has
produced 2.5 million carats, becoming the only mine in recorded history to have
produced two 1,000+ carat diamonds.