A total of 54 out of State-run miner Coal India Limited’s (CIL’s) 120 coal mining projects are delayed, the company says in its latest financial statement. CIL reports that the major reasons for the delays in completion of the 54 projects are the time taken in securing mandatory environment and forest clearances, land possession complexities and issues relating to resettlement and rehabilitation of project-affected people.