Rio Tinto faces $1.9bn cost blowout, further delays at Oyu Tolgoi copper-gold mine

World’s No.2 miner Rio Tinto (ASX,
LON, NYSE:RIO) is once again in deep trouble in Mongolia, but this time is not related
to government questioning the legitimacy of the ongoing underground expansion
of its giant Oyu Tolgoi copper-gold-silver mine, but the costs and schedule of
the project.

The company revealed on Tuesday that difficult ground conditions could blow out the estimated cost of the expansion (currently pegged at $5.3 billion) by as much as an additional $1.9 billion, causing further delays of up to two and a half years.

First sustainable production is now
expected between May 2022 and June 2023, though Rio said a final estimate
cost and schedule would be announced in the second half of 2020.

The mining giant noted the update would reflect the “preferred mine design approach” since changes to planned underground infrastructure such as the ore handling system and access ramps have to be considered.

Ground conditions are more
challenging than expected and we are having to review our mine plan.

“Delays are not unusual for such a large and complex project, but we are very focused as a team on finding the right pathway to deliver this high value project,” Rio Tinto group executive, growth and innovation, Stephen McIntosh, said in the statement

The company also said it was reviewing the carrying value of the project and could announce an impairment charge when it announces half-year results next month. Rio has also agreed to build a power plant to supply the mine, which will make the final cost of the project even higher.

Turquoise Hill (TSE, NSYE: TRQ), the Rio-controlled company that owns 66% of Oyu Tolgoi, said they have already identified a number of mine designs to address the stability risks associated with the original expansion design.

Ground conditions are more challenging than expected and we are having to review our mine plan.

Stephen McIntosh, Rio Tinto.

“Current information indicates that Oyu Tolgoi mineral reserves will not be materially impacted by the Hugo North mine design options being considered; however, ongoing reviews will be considered as the work progresses,” the Canadian miner said in a separate statement.

Issues with the underground project first emerged in October, when a nine-month delay to sustainable production was announced due to technical problems.

The companies have been using block-caving
mining at the asset. Although technically challenging, it’s deemed as one of
the most cost-effective mining methods for extracting ore buried deep below the
surface.

For block-caving to effectively work,
weak and fractured rock needs to collapse under pressure from gravity. Rio
Tinto chief executive Jean-Sébastien Jacques had previously mentioned that rock
collapses too easily at Oyu Tolgoi.

“Starting a block cave correctly is critical to its long-term safety and viability. Analysis suggests that the current mine design carries stability risks leading to a number of alternative mine designs being considered with work currently at the conceptual study phase,” Edward Sterck, analyst at BMO Capital Markets, said in a note to investors. “The alternative plans may require relocation of critical underground infrastructure and a change in mining sequence.”

Rio has been stepped up efforts to find new copper deposits worth of being developed into mines, since demand for the industrial metal is expected to grow further as the world shifts to cleaner forms of energy. 

The company’s board of directors approved the underground expansion of the massive Mongolian mine in the Gobi desert three years ago, but progress has been slow due to a series of disagreements between Rio and the country’s government, including differences over taxes owed and a power contract.

Oyu Tolgoi was discovered in
2001 and Rio gained control of it in 2012. Once finished, the expansion is
expected to lift the mine’s production from 125–150kt this year to 560k tonnes
of copper concentrate at full tilt from 2025, making it the world’s
third-largest copper mine.