Lithium project developer Nemaska Lithium has made “good progress” during the past months on the construction at its Whabouchi mine and the detailed engineering at its Shawinigan plant, president and CEO Guy Bourassa reported on Thursday.
The Quebec-focused junior, which had been forced to set a new pace for construction at the mine after a project cost blow-out left it short of cash, said that 55% of the detailed engineering of the Shawinigan electrochemical plant was completed at the end of last month.